Sawaed Al-Hamra Real Estate Project 105
Main video
Engineering Report
Detected changes
Completion of the top floor slab casting and brick masonry for facades and typical floors, with safety scaffolding remaining in place.
Commencement of interior wall plastering and ceramic tile installation in selected areas, alongside ongoing electrical and plumbing installations.
Progress reading
The images reflect substantial development in the concrete structure (95%) compared to the previous visit, alongside tangible progress in finishing works (30%), which are now clearly visible in the plastering and wall cladding stages.
vs previous visit
Compared to the previous visit, the entire concrete structure for the upper floors has been completed, and masonry and interior finishing works have expanded significantly, whereas the previous visit showed the building in its early structural stages.
Expected next milestones
Completion of plastering works for the entire building, commencement of roof waterproofing, and intensification of electrical and plumbing installations on the remaining floors.