Al Hamra 104 Project
28 Jun 2025

Sawaed Real Estate Al Hamra 104 Project

6%Overall▲ +5% · vs previous visit

Main video

Engineering Report

The project has transitioned from the excavation phase to the concrete structure phase. Currently, reinforcement and pouring of the concrete raft foundation are underway using concrete pumps, following the completion of excavation and general site preparation.
Detected changes
Concrete Structure100%

Execution of steel reinforcement for the concrete raft foundation across the entire land area, with the commencement of pouring operations using two concrete pumps and the presence of transit mixers on-site.

General Site95%

Completion of excavation works and shoring of site perimeters, along with the installation of temporary fencing and project signage, and the mobilization of heavy equipment and construction materials.

Progress reading

The visual evidence aligns with the increase in completion rates. It clearly shows the transition beyond the excavation stage (20%) and the actual commencement of concrete works (8%) through the raft pouring, which explains the surge in progress compared to the previous visit.

vs previous visit

Compared to the previous visit, which showed the site in the early stages of excavation with only one excavator present, the current visit reveals a radical transformation with the completion of excavation, the commencement of concrete foundation pouring, and the presence of specialized work crews and pouring equipment.

Expected next milestones

Completion of the concrete raft foundation pouring, and the commencement of steel reinforcement and formwork for column necks and basement walls, if applicable.

Progress

0%OverallAverage item progress
0/5 completeavg ▲ +5%
Excavation Works▲ +15%
0%
Concrete Works▲ +8%
0%
Finishing Works
0%
Electrical Works
0%
Plumbing Works
0%

3D Visualization

Drone Footage

On-site Photography

ShareChat on WhatsApp