Sawaed Real Estate Al Hamra 104 Project
Main video
Engineering Report
Detected changes
Execution of steel reinforcement for the concrete raft foundation across the entire land area, with the commencement of pouring operations using two concrete pumps and the presence of transit mixers on-site.
Completion of excavation works and shoring of site perimeters, along with the installation of temporary fencing and project signage, and the mobilization of heavy equipment and construction materials.
Progress reading
The visual evidence aligns with the increase in completion rates. It clearly shows the transition beyond the excavation stage (20%) and the actual commencement of concrete works (8%) through the raft pouring, which explains the surge in progress compared to the previous visit.
vs previous visit
Compared to the previous visit, which showed the site in the early stages of excavation with only one excavator present, the current visit reveals a radical transformation with the completion of excavation, the commencement of concrete foundation pouring, and the presence of specialized work crews and pouring equipment.
Expected next milestones
Completion of the concrete raft foundation pouring, and the commencement of steel reinforcement and formwork for column necks and basement walls, if applicable.