Sawaed Real Estate Al Hamra 104 Project
Main video
Engineering Report
Detected changes
Concrete pouring for the floor slab is currently underway using pumps, following the completion of reinforcement steel laying and the distribution of red hollow blocks.
Installation of white PVC drainage pipes and orange electrical conduits within the slab reinforcement mesh prior to concrete pouring.
Presence of pouring equipment (two concrete pumps) and mixer trucks, with organized traffic flow for entry and exit in the building's immediate vicinity.
Progress reading
The visual evidence is consistent with the increase in concrete work to 15%, as work has transitioned from foundations/columns (in the previous visit) to the slab pouring stage. The 7% increase reflects the completion and full preparation of the current ceiling structure.
vs previous visit
Compared to the previous site visit photos (photos 21 to 26), we observe a radical transition from the preparation of floor reinforcement and ground beams to the casting of upper slabs. This confirms that excavation work is 100% complete and the structural framework is actively rising.
Expected next milestones
Completion of casting the entire roof slab area, commencement of formwork removal after the required curing period, followed by the transition to the columns of the next floor.