Sawaed 103
12 May 2025

Sawaed Real Estate Al Rawdah 103 Project

13%Overall▲ +10% · vs previous visit

Main video

Engineering Report

The Sawaed 103 project site was visited on May 12, 2025, where significant progress in the structural framework was observed. Work is currently underway on pouring the columns for one of the upper floors using a concrete pump, while masonry work continues on the lower floors alongside the installation of mechanical and electrical services.
Detected changes
Concrete Structure100%

Completion of concrete pouring for the lower floor slabs and transitioning to the formwork and reinforcement phase for the current floor columns, with concrete pumps and mixers on-site to begin the pouring process.

Masonry Works95%

Commencement of wall construction using red bricks on the floors where concrete formwork has been dismantled.

Plumbing and Electrical Works90%

Installation of PVC drainage pipes and electrical conduits within the slabs and columns currently under construction.

Site Infrastructure and Facades100%

The site is enclosed by a temporary security fence featuring the project's visual identity, with organized movement of heavy equipment in the surrounding street.

Progress reading

The notable increase in concrete work (+20%) is clearly evident through the structural frame rising by a full floor since the previous visit. Additionally, the commencement of finishing works (7%) and plumbing (5%) aligns with the appearance of masonry work and piping installations in the current photos, which were not present previously.

vs previous visit

Compared to the previous site visit photos (21-24), the project has progressed from the ground/first floor ceiling formwork stage to the casting of upper floor columns, with the commencement of masonry work which was entirely absent during the previous visit.

Expected next milestones

Completion of casting for the current floor columns, commencement of formwork for the next ceiling, and intensifying masonry work on the structurally completed floors.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +10%
Concrete Works▲ +20%
0%
Finishing Works▲ +7%
0%
Plumbing Works▲ +5%
0%
Electrical Works▲ +6%
0%

3D Tour

Drone Footage

360 Video

On-site Photography

ShareChat on WhatsApp