Sawaed Real Estate Al Rawdah 103 Project
Main video
Engineering Report
Detected changes
Completion of concrete pouring for the lower floor slabs and transitioning to the formwork and reinforcement phase for the current floor columns, with concrete pumps and mixers on-site to begin the pouring process.
Commencement of wall construction using red bricks on the floors where concrete formwork has been dismantled.
Installation of PVC drainage pipes and electrical conduits within the slabs and columns currently under construction.
The site is enclosed by a temporary security fence featuring the project's visual identity, with organized movement of heavy equipment in the surrounding street.
Progress reading
The notable increase in concrete work (+20%) is clearly evident through the structural frame rising by a full floor since the previous visit. Additionally, the commencement of finishing works (7%) and plumbing (5%) aligns with the appearance of masonry work and piping installations in the current photos, which were not present previously.
vs previous visit
Compared to the previous site visit photos (21-24), the project has progressed from the ground/first floor ceiling formwork stage to the casting of upper floor columns, with the commencement of masonry work which was entirely absent during the previous visit.
Expected next milestones
Completion of casting for the current floor columns, commencement of formwork for the next ceiling, and intensifying masonry work on the structurally completed floors.